MBTA completes tunnel signal swap, targets March 2027 operation at Copley

Crews installed 12.5 miles of new cable during a nine-day closure, clearing the path for Type 10 cars and ADA-compliant platforms on the C Branch.

By Elena Greco ·

Illustration for: MBTA completes tunnel signal swap, targets March 2027 operation at Copley
Illustration generated for this article, not a news photograph.

The Massachusetts Bay Transportation Authority finished a nine-day overhaul of the Green Line’s central tunnel signal system on Wednesday. The work replaced infrastructure that dates back to the late 1800s, the same era as the first electric trolleys in North America. The new system is scheduled to become operational at Copley in early March 2027.

During the shutdown, which ran from November 10 to November 18, crews installed 12.5 miles of signal cable. This adds to 56 miles of new signaling cable placed during previous diversions. Workers also installed one mile of fiber-optic cable and advanced connections for the modernized system. The authority stated that this phase of work concluded with the successful completion of the signal power cutover at Copley.

Phillip Eng, the interim Secretary of Transportation and MBTA General Manager, said the modern signals provide the operational flexibility needed to run the new Type 10 Green Line cars. Those vehicles are set to enter passenger service next year. Eng noted that the signal upgrades are a prerequisite for operating the new fleet. He cited the Healey-Driscoll Administration and the Legislature for supporting these investments.

The nine-day closure also served as the final multi-day shutdown for the Green Line C Branch Station Accessibility Improvements project. Crews worked at seven above-ground stations: Englewood Avenue, Dean Road, Tappan Street, the consolidated Fairbanks Street/Brandon Hall station, Summit Avenue, Saint Paul Street, and Hawes Street. The goal is to make all stations on the C Branch accessible. The Fairbanks Street stop is now permanently closed, with service consolidated at the upgraded Brandon Hall stop.

Structural steel for platform canopies was installed at the Brandon Hall and previous Fairbanks Street ramps. Crews removed existing inbound platforms and shelters at Hawes Street and Summit Avenue. They also installed lighting, signage, and trackside landscaping at multiple locations. The first phase of the project raises platforms to eight inches to meet ADA standards for the current vehicle fleet. A future second phase will add another six inches to reach a 14-inch height, allowing for level-boarding with the Type 10 cars.

Beyond the signal and accessibility work, crews performed maintenance at other stations. They replaced ties and ballast at Symphony and completed track work at switch areas in Park Street. Security upgrades included the installation of cameras at Park Street, Downtown Crossing, and Broadway. The authority stated that multi-day outages are necessary to combine efforts from multiple contractors and maximize productivity for routine maintenance and upgrades.

More News · Report a business · Got a Story?

Get Hot News Report in your inboxBig-city news, all in one place. Free, a few times a week, unsubscribe any time.

Related stories

Get Hot News Report in your inboxBig-city news, all in one place. Free, a few times a week, unsubscribe any time.